Project Update - June 2016

Works are now underway in Bong Bong Road following the removal of a 250m long abandoned asbestos water main, by a licenced contractor, which was in the way of the new stormwater pipe.

The majority of works required for this construction project are expected to be finished by 30 June 2016. Retaining walls are now complete and stormwater works are half finished.

Driveways will be finished within the first few weeks of July, bringing the job to a close.

Share on Facebook Share on Twitter Share on Linkedin Email this link

This work has now been completed

<span class="translation_missing" title="translation missing: en.projects.blog_posts.show.load_comment_text">Load Comment Text</span>