Will I still be able to walk into Mittagong along the path beside the golf course?

    Yes access will be maintained for Willow Vale residents to walk into Mittagong using the path along the golf course fence line.

    What will happen with bus services while the bridge is closed?

    We have been working with Berrima Buslines to ensure that their services continue while the work is underway.

    Drivers will advise passengers of changed routes but to learn more please call 02 4871 3211 or

    Who has been notified about the road closure?

    Emergency services and transport providers have been notified about the planned works and will be kept informed.

    Residents in Willow Vale, Balaclava and Braemar will receive a second Community Update in the week of 12 September 2016. Click here to view it.

    Why can't the old bridge be left there while the new work is completed?

    The temporary closure of Railway Terrace is an essential part of the new works as the earthworks for the new bridge will extend over the existing road on Railway Terrace. Further to this, John Holland Rail also needs to remove the old timber bridge to complete their works. The reopening of Railway Terrace will occur when the traffic signals have been installed at the intersection of the highway.