Share Project Update - June 2016 on Facebook
Share Project Update - June 2016 on Linkedin
Email Project Update - June 2016 link
Works are now underway in Bong Bong Road following the removal of a 250m long abandoned asbestos water main, by a licenced contractor, which was in the way of the new stormwater pipe.
The majority of works required for this construction project are expected to be finished by 30 June 2016. Retaining walls are now complete and stormwater works are half finished.
Driveways will be finished within the first few weeks of July, bringing the job to a close.
Share Project Update - March 2016 on Facebook
Share Project Update - March 2016 on Linkedin
Email Project Update - March 2016 link
Bong Bong Road improvements are steadily progressing with all trees now removed and Council resolving to award a contract for construction to Cadifern Civil at the 24 February 2016 meeting.
Weather permitting, the contractor is expected to start working on site in the third week of March.
It is anticipated that the work will take approximately 10 weeks to complete.
For further information please contact Trevor Grant (02) 4868 0824 or Josh Provis (02) 4868 0569.
Share Project Update - November 2015 on Facebook
Share Project Update - November 2015 on Linkedin
Email Project Update - November 2015 link
Work on Bong Bong Road improvements is continuing. We distributed an updated set of plans to affected Bong Bong Road residents in July and are currently waiting to confirm when water main renewal work will occur. Quotes have also been sought for the removal of 18 trees.
At this point in time, road works are scheduled to commence in February 2016 but this is dependent on many factors including weather. As we confirm dates and impacts of the various stages we will notify residents in Bong Bong Road and the wider area. For further information please contact Trevor Grant (02) 4868 0824 or Josh Provis (02) 4868 0569.
Share Letters and plans issued to Bong Bong Road property owners on Facebook
Share Letters and plans issued to Bong Bong Road property owners on Linkedin
Email Letters and plans issued to Bong Bong Road property owners link
Property owners along Bong Bong Road, between Belmore Street and
Mary Street, will shortly receive a letter from Council's Design Team to
outline the proposed upgrade and seek feedback.
A copy of plans proposed
for the length of street will be enclosed with the letter and these can be
viewed in our Document Library.